Workplan » History » Version 17

Steve Welburn, 2012-11-13 12:30 PM

1 1 Steve Welburn
h1. Workplan
2 2 Steve Welburn
3 3 Steve Welburn
{{>toc}}
4 3 Steve Welburn
5 2 Steve Welburn
The work of the project is divided into four work packages (WP).
6 2 Steve Welburn
7 13 Steve Welburn
{{include(WP1 Training Material Design)}}
8 3 Steve Welburn
9 15 Steve Welburn
{{include(WP2 Test and evaluation)}}
10 3 Steve Welburn
11 17 Steve Welburn
{{include(WP3 Embedding)}}
12 3 Steve Welburn
13 2 Steve Welburn
h2. WP4 Communication and Management
14 3 Steve Welburn
15 3 Steve Welburn
h3. WP4.1 Project management
16 3 Steve Welburn
17 9 Steve Welburn
The project will be managed on a day-to-day basis by the PI, with project meetings held weekly to assess progress and problems. This has been our practice throughout the Sound Software project and previous JISC-funded projects. The CIs will participate in the management process to ensure compatibility and continuity with the requirements of the Sound Software project from a management and technical perspective respectively.
18 3 Steve Welburn
19 3 Steve Welburn
h3. WP4.2 Dissemination
20 3 Steve Welburn
21 3 Steve Welburn
The project results will be disseminated through blog posts, Twitter, and official reports on the project's website. Results will also be presented at discipline-specific conferences (ISMIR, DAFx), and to other similar UK-based research institutions via the partnership with the Sound Software project.
22 3 Steve Welburn
23 3 Steve Welburn
h3. WP4 Deliverables
24 3 Steve Welburn
25 3 Steve Welburn
* D4.1 Project site and feed.
26 8 Steve Welburn
* D4.2 Final report and publication of the material in the "Jorum":http://www.jorum.ac.uk/ repository.
27 7 Steve Welburn
28 7 Steve Welburn
29 7 Steve Welburn
h2. References
30 7 Steve Welburn
31 7 Steve Welburn
??"DaMSSI final report":http://www.dcc.ac.uk/webfm_send/532??