h1. Project and job description for 2013 reboot
2 1 Chris Cannam
3 1 Chris Cannam
The purpose of the project is to develop a proof-of-concept Reproducible
4 1 Chris Cannam
Research Repository (RRR) to associate records of experimental work in
5 1 Chris Cannam
the audio and music domain with the software and datasets used and any
6 1 Chris Cannam
resulting publications.
7 1 Chris Cannam
8 1 Chris Cannam
The Repository is intended to be a lightweight source of information
9 1 Chris Cannam
about publications and the experimental work they describe, connecting
10 1 Chris Cannam
experiments with links to the software versions and datasets used and
11 1 Chris Cannam
documentation about how to reproduce the experimental setup. The
12 1 Chris Cannam
intention is to store metadata and descriptive documentation only;
13 1 Chris Cannam
software and datasets will be expected to be hosted in other suitable
14 1 Chris Cannam
repositories such as code.soundsoftware.ac.uk, Github, institutional
15 1 Chris Cannam
repositories, etc, and the RRR will link to these.
16 1 Chris Cannam
17 1 Chris Cannam
The project is scheduled to take 5 months for 1 developer, to be
18 1 Chris Cannam
structured as follows:
19 1 Chris Cannam
20 2 Chris Cannam
 * 3 weeks - Review and document existing work in this field, including
21 2 Chris Cannam
  an incomplete earlier project within QM, and liaise with data
22 2 Chris Cannam
  repository team in QM ITS in order to establish whether an
23 1 Chris Cannam
  existing solution can be applied
24 2 Chris Cannam
 * 1 week - Decide and justify whether to use an existing solution or
25 1 Chris Cannam
  develop a new one
26 1 Chris Cannam
27 1 Chris Cannam
then either (if developing a new solution)
28 1 Chris Cannam
29 2 Chris Cannam
 * 2 months - Develop a minimal new system as a proof-of-concept 
30 2 Chris Cannam
 * 1 month - Deploy to internal test users, revise according to feedback
31 2 Chris Cannam
 * 1 month - Document the system and determine the appropriate next steps
32 1 Chris Cannam
  to take to make a robust public-facing implementation
33 1 Chris Cannam
34 1 Chris Cannam
or (if using an existing one)
35 1 Chris Cannam
36 2 Chris Cannam
 * 1 month - Deploy and tailor existing solution
37 2 Chris Cannam
 * 1 month - Deploy to internal test users, revise according to feedback
38 2 Chris Cannam
 * 1 month - Configure and deploy robust public-facing implementation
39 2 Chris Cannam
 * 1 month - Document the system and determine appropriate next steps
40 1 Chris Cannam
41 1 Chris Cannam
The developer must be confident with at least one web development
42 1 Chris Cannam
platform, and experienced enough to be able to make the appropriate
43 1 Chris Cannam
decisions about technology and infrastructure based on experience with
44 1 Chris Cannam
multiple platforms and frameworks.